Tuesday, 1 September 2020

Landscaping

Darren did a very neat job levelling the ground around the house when we had the bobcat for the water tank and put some of the piled top soil in place at the entrance.
Some stones were also collected and placed as corner stones at the front door.


My first outing to the Australian Native Nursery in Oakford was with Benny, who seemed to think 40 tube stock plants was plenty and 'Grandma I think you have enough plants now. Do you know how much this is going to cost?!' Lol
At 60 plants we headed off, I went back a few days later and picked up another 20 plants.


I built some steps up the bank as the rolling gravel is lethal, they turned out ok :)

All 80 tube stock plants are in the ground some in front of the house, the rest are on the bank and bushes along the top.


I even had some help with planting thanks to Justin, Lou and Kylie :)






Water tank and no rain!

Thanks to you Mum, for the water tank donation, it is so much appreciated.
If you could just get out there in the back yard and do a bit of a jig with your walker (rain dance) it would also be appreciated.
With the tank ordered we needed to get in the bobcat again to make the  pad.



First to dig down so the water would run in and then lay a cracker dust pad to support the tank.



It's called a wet system because water stays in the pipes underground unless you flush the system

The truck arrived and it looked way to big lol, once it was tipped off the truck and pushed into position it looked as it should.



The down pipes have rain heads to keep leaves out of the tank.


There's also a release screw to clear the stagnate water at the end of winter and first rain with dust bird droppings at the begining of winter.

All topped off!

 The roof is finished and all under it is dry!
Watching someone work when they know what they're doing is such a pleasure and an opportunity to learn.
Darren started with the lining boards which will be seen under the verandahs, the sitting area and entrance.


The batons were spaced at 600mm all the way to the top and then the rolls of Anticon were laid out in overlapping sequence.




The long north sheets were on in just a few hours, the same for the west end.


The Western Red Cedar weatherboards filled the gable end and barge finished it off.


The valleys and hips are so neat and tidy.

It's all looking so beautiful


Tuesday, 28 July 2020

More work and a little bit of art.


My photos are the only way I can jog my remember on what and how much work is getting done (mostly by Darren).
With the concrete set the remainder of rafters went up quickly.


One evening we went out the farm to do something or other, Darren went to the shed and I was just enjoying the moon shining through the rafters, as Darren drove back up the lights from the car moved from one place to another on the rafters until it lit Bruce majestically.


Darren cut the bird's mouths so accurately they lined up like little soldiers.... everything lines up so beautifully :)


Benny spent a week with us and helped with the timbers in the 'foyer' (sounds so grand eh?!).



The foyer has a lowered ceiling with exposed rafters and reclaimed pressed tin artistically painted .. or at least artistically wire buffed with the grinder.



Anyone who has experienced my arty self would know that it can be a little underwhelming, especially if it involves sewing! However, I have surprised myself with the distressed tin!

The other piece of art work I've been playing with is the house sign, the font is Higher Jump, which gives a muddy splash look. I've got a better idea of how to use the router trimmer to engrave the timber after practicing a few times.


The sign will include a Willy Wagtail ... wherever we have travelled we have had a Willy or Wilma travel with us, stopping to chatter on a branch and move on.


We've made it into a story of our own whereby it's the same Willy Wagtail we see each time, coming along for the trip or showing us the way (they do all look the same lol).
So today ... the gutters are finished and the ceiling in the foyer is up (just needs a bit of quad to finish off).



Tomorrow we'll start the sheeting by putting up some of the 141, 6 metre lengths of pine lining that I've been staining down in the shed. 

Monday, 29 June 2020

All set in concrete!

As soon as Bruce was erect and holding up his end (the ridge beam) it was time to put up the poles and fix the fascia which all happened very quickly.
Next came the rafters and end gables. Some mornings were a little chilly with frost across the paddock, rain occasionally and a rainbow ending at our pot of gold!

I love timber, the smell the feel and the colours of a good rich wood. This is a branch piece from Bruce that I've planed, sanded and oiled ... just gorgeous. 
We're hoping to slab a limb and use it for the collar ties in the main room. 
I also love looking for the faces that live in the timber grain.

 
The entrance timbers are book ended after discarding a couple of other pieces. It's still to be stained the cedar colour.
A sign saying "Muddled Up Manor' will be carved and used as a collar tie and hung across the entrance.


This morning we arrived at the house after an horrendous night of gusting winds and rain to find it a little on the piss! Which would have been just fine if it hadn't been the day the concrete was coming to secure the poles in place for ever. After a very hectic and stressful 45 minutes which included a rope tied to the car and driven very slowly, the poles were back in place. 
The truck arrived and the pour went without a hitch with a huge thank you to our new T A Clinton running with the barrow.




Mel also worked as a T A helping with the new valley timbers at the entrance, not realising that she needed to read minds, anticipate and run just a bit faster up the ladder, the timber she was expected to be holding onto ended up bumping into Darren... nothing broken lol.



Tuesday, 16 June 2020

Bruce's Erection!

I had planned and expected to update this blog each month with a 'Monthly Round Up', it's obvious now that the build is moving along so fast that weekly updates are more likely, so .....
Bruce was chopped off at his ankles last week, it fell exactly as planned, the post area was selected and trimmed, strapped to the back of the car and dragged to the site.



The top 'Y' junction was notched with the chainsaw.

The facia was bolted loosely to the pine pole and Bruce, set under a tripod and lifted with a block and tackle then propped.
A higher tripod was put in place and lifted Bruce a bit higher.

The straps, fulcrum and car winch took over, the car needed to be chocked as the weight was greater than the car!
Slowly but surely Bruce was erected into his place of honour in the centre of the main room.


PS. I rang Clinton to confirm we could take a tree from the farm for the centre pole, he wanted to know which tree we had in mind... I sent him a picture and told him it had the least top story of all the trees around and was at the back, more out of sight and least likely to be missed on the horizon.
He looked at the picture and declared "Oh Nooo!! That's Bruce, you can't take Bruce he's my friend!! It would have been lovely if a more tree like name had been his first thought ... but there you are ... it's Bruce!!!
Thanks for your sacrifice Bruce and welcome to our home.

Wednesday, 10 June 2020

Not even the middle of June

The planning how to cut the notches in the pole tops took a little while, we tried the drop saw, it was very slow. We bought a reciprocating saw with a 300mm blade, Darren made a jig that looked like it came from a medieval torture dungeon, it worked a treat. The two internal cuts were started with a circular saw and finished with a multi tool, very neat!

We hired a mini excavator with a power head and 600mm auger attachment for the weekend, it worked a treat to strap the waste and storm water pipes to for the trip home ..  wasn't overhanging the car or trailer if you don't look between the vehicles!

As soon as we get to the farm it's unload and start playing. The moon was full (we'd watched it and the incredible sunset all the way home) which gave plenty of light, headed home to sleep after 4 holes dug.

So the weekend has been a wonderful success, all holes dug, waste plumbing and storm dug, laid and covered, the drain for Agi pipe is dug (waiting on pipe), the drive ways are excavated and gravel coated.


The weather has been stunning, even a bobtail managed a cruise through the site.


The timber was delivered today, the truck driver had coffee with us and during the chat about the house build he asked 'When do they start?' in regard to the builders!! Hahahaha Tag we're it!!!!